外国投资者在越南值得信赖的合作伙伴

门窗、栏杆与洁具

木门与钢门安装

门洞检查、从门框组装到门锁和成品保护的木门安装九个步骤、钢门及防火门安装,以及常见错误。

  • World Steel Group
  • 发布于
  • 阅读约 8 分钟
木门与钢门安装
本文内容
  1. Preparation
  2. Checking the opening (timber doors)
  3. Timber door sequence
  4. Steel doors and fire doors
  5. Common mistakes
  6. Reference standards

本文正文为英文版,中文译文正在准备中。

World Steel installs timber doors for offices and meeting rooms and steel doors (including fire doors) for plant rooms, escape stairs and stores in the final stage of a project, after plastering and floor finishes have been accepted. Defects in timber doors repaired on site rarely reach workshop quality, so checking the openings and protecting the product come first.

木门与钢门安装, 图 12

Preparation

  • Openings built and plastered, with clear dimensions and lintel levels accepted by the supervising consultant and the project management team. Toilet doors: toilet tiling and threshold stones completed and accepted.
  • Materials of the contract type and to the drawing sizes, well wrapped against scratches and stored in a dry place.
  • Frame fixing screws line up with the concrete blocks built into the wall.
  • Tools: drill, laser, screw gun, tape measure, brad nailer, saw, compressor.

Checking the opening (timber doors)

CriterionPermitted deviation
Opening size±3 mm
Wall thickness±2 mm
Wall twist±2 mm
Squareness of the opening±3 mm per side

Timber door sequence

StepWorkControl
1. Setting outRestore the +1.00 m datum on the plaster or reveals.Head level of the frame.
2. Frame assemblyAssemble the frame on a flat floor; tight joints; pre-drill screw holes so the frame does not split.Frame size against the opening.
3. DrillingDrill holes for expansion screws in the reveals to the number shown on the drawings.Aligned with the built-in concrete blocks.
4. Fixing and adjusting the frameSet the frame in the opening; plumb it with a laser; wedge it with timber wedges; fix with D9/D10 steel screws.Recheck plumb and square before hanging the leaf; call the supervising consultant to accept the frame.
5. Filling the gapInject expanding foam into the frame gap (depending on the project method); trim excess foam and clean.Gap filled, no foam on the frame face.
6. Hinges and leafFit hinges flush and tight to the leaf; hang the leaf to size; hinge number, spacing and type as designed. Fix the hinge-side jamb first, adjust the gap on the lock side, then fix the lock-side jamb.Test opening and closing; even, flat gaps.
7. ArchitravesEven margin from frame to architrave as drawn (usually 15 mm); pins 200–250 mm apart; crisp mitres.Architraves plumb and true.
8. Locks and handlesCut the lock pocket (possibly before hanging the leaf) and the strike in the frame; fit the lock after the leaf is accepted.Test the lock.
9. ProtectionTouch up and wrap in plastic until handover.No cleaning chemicals that discolour the finish.

木门与钢门安装, 图 21

Steel doors and fire doors

  • Check the plastered opening against the shop drawing; mark levels from the +1000 datum.
  • Fix the frame with D9/D10 steel screws, expansion bolts or brackets as per the shop drawing, into the concrete blocks in the wall; wedge and check plumb and square before tightening; plug the screw holes in the frame with rubber caps.
  • Hinges flush; corrosion-resistant screws tightened flush with the hinge; adjust the leaf gap, then fix the lock-side jamb.
  • Fit locks and door closers after the leaf is accepted. Fire doors: fill the frame-to-wall gap with fire-rated foam or seals where the design requires it.
  • Apply silicone, clean, carry out final acceptance and cover with protective film.

Common mistakes

MistakeRemedy
Opening built to the wrong size and cut backAccept the openings before taking over the area
Architraves not tight to the wallAccept wall flatness after plastering; fill small gaps with foam and silicone
Cracked architraves, mitres not meetingPre-drill, machine cut mitres, replace damaged pieces
Wall damaged during installationDrill in the right direction, use timber wedges, repair before final painting
Wall paint on architravesProtect with plastic; painters clean up without stripping chemicals
Missing hinge screwsFit all screws
Architrave proud because it sits over the skirting; gaps at the skirting baseReplace the skirting, refit the architrave; use full-length skirting pieces

Reference standards

The edition in force when the contract is signed applies.

  • TCVN 9366-1:2012 Doors and windows – Part 1: Timber doors and windows
  • TCVN 9366-2:2012 Doors and windows – Part 2: Metal doors and windows
  • TCVN 5674:1992 Finishing works in construction – Execution and acceptance

标签

  • construction-method
  • doors
  • fit-out

分享