Menuiseries, garde-corps et équipements
Pose des garde-corps, appareils sanitaires et mobilier fixe
Six étapes pour les garde-corps, de l’implantation des poteaux et des ancrages aux mains courantes et au verre, la séquence pour les sanitaires et le mobilier fixe, et leur protection.

Dans cet article
Le corps de cet article est publié en anglais ; la traduction française est en préparation.
Stair, corridor and platform railings, sanitary fixtures and built-in units are among the last items installed, but they directly affect the safety and everyday use of a factory. World Steel installs them to approved shop drawings, fixes them to the structure with accepted chemical anchors or expansion bolts, and protects them until handover.

Installing railings
| Step | Work | Control |
|---|---|---|
| 1. Drawings | Prepare the installation method. Railings longer than 3,000 mm made of many modules are best adjusted to site dimensions under 3,000 mm to save material and labour. | Approved shop drawings. |
| 2. Post positions | Set out the base plates from the survey grid lines and the +1000 datum; drill the concrete beams and slabs; set threaded rods in adhesive or use drop-in anchors. | For chemical anchors: accept the hole depth (usually 100 mm) and clean the holes before injecting adhesive. |
| 3. Posts | Fit the base plates and bolts; cut the rod ends so they do not stand above the finished surface. Where welded to cast-in parts, use matching filler material. | Base plate level against the finished level; posts plumbed with a spirit level. |
| 4. Handrails | Fix the handrail to the post tops: timber handrails by screws, metal ones by bolts or TIG welding. After checking, grout the base plates with non-shrink grout (clean and dampen the concrete first). | Railing line vertical and horizontal. |
| 5. Glass (if any) | Fit the glass panels into the clamps in the planned sequence; check and retighten. | Gaskets and supports not visible. |
| 6. Finishing | Check plumb and level; welds and fixings tight; clean glass, handrails and posts with a soft cloth. | Protection in place while following trades work. |
Sanitary fixtures
- Installed after the waterproofing, toilet tiling and water supply and drainage are complete and accepted.
- Sequence: vanity frames and stone tops; basins; WCs; taps, showers and floor drains; function test.
- Wrap fixtures immediately after installation: uncovered WCs and basins scratch easily, and so does the plating on taps and showers.
- Cover fixture outlets so mortar and debris cannot enter the drains.
- Wear gloves when fitting lights and socket covers to keep ceilings and walls clean.
Built-in units
- Check site dimensions and mark the unit positions.
- Erect the side panels, shelves and modules; check level and plumb; screw them to the wall.
- Join the modules, fit worktops and appliances; drill for hinges, hang doors, fit handles and accessories; check and hand over.
Common mistakes
| Mistake | Prevention |
|---|---|
| Rods anchored too shallow, holes not cleaned | Accept depth and clean the holes before injecting adhesive |
| Rod ends above the finished surface | Cut the rods after the base plates are fixed |
| Railing not straight, handrail at uneven heights | Set out from survey lines and check every span with a level |
| Scratched fixtures, drains blocked with mortar | Wrap and cover immediately after installation |
Reference standards
The edition in force when the contract is signed applies.
- TCVN 5674:1992 Finishing works in construction – Execution and acceptance
- TCVN 7505:2005 Code of practice for application of glass in buildings – Selection and installation