Le partenaire de confiance des investisseurs étrangers au Vietnam

Fondations et sous-sols

Méthode de réalisation des pieux forés

Matériel, contrôle du fluide, forage, mise en place des cages, curage et bétonnage des pieux forés, avec les incidents courants et leurs remèdes.

  • World Steel Group
  • Publié le
  • 3 min de lecture
Méthode de réalisation des pieux forés
Dans cet article
  1. Equipment and materials
  2. Work sequence
  3. Typical problems and remedies
  4. Acceptance
  5. Reference standards

Le corps de cet article est publié en anglais ; la traduction française est en préparation.

Bored piles are used when loads are heavy, the bearing layer is deep, or driving and jacking piles would affect neighbouring buildings. Every method follows one of two principles: drilling with a casing, or drilling without a casing (under supporting fluid, or reverse circulation). This article summarises the procedure World Steel applies to bored pile foundations for factories and office blocks.

Méthode de réalisation des pieux forés, photo 12

Equipment and materials

Equipment, materialUse
Reverse circulation rig or bucket drilling rigDrilling the hole
Ultrasonic borehole loggerMeasuring hole depth and verticality
Grab excavatorLoading spoil onto trucks, breaking the existing slab
Air-lift cleaning unitRemoving sediment from the base of the hole
Generator, welding sets, bar cutters and bendersFabricating and welding cages
8"–10" tremie pipes and hopperBase cleaning and underwater concreting
Temporary casingStabilising the top of the hole
Steel plates and sectionsCovering fluid pits and holes, cage support frames
Polymer or bentonite powder, sodaMixing the supporting fluid
Crawler craneHandling casing, cages and heavy equipment

Work sequence

StepWorkControl
1. Setting out, casingSet out the pile centre; lower the casing with the crane and push it down to existing ground level with an excavator.Casing coordinates checked with a total station.
2. Fluid checkTest the fluid before drilling and before concreting.Indicative values for polymer at 21 °C: viscosity 32–50 s (Marsh funnel), pH 8.5–11.5, density 1.0–1.1, sand content below 2%.
3. DrillingCentre the tool on the casing; level the rotary table; keep the kelly vertical throughout drilling.Verticality with a spirit level; hole depth and diameter.
4. Cage installationLower the cage section by section with the design lap length and link spacing at the splices. For top-down basements, insert the kingpost and weld it to the cage.Lap length, spacers, cage top level; the kingpost welded to the cage at three evenly spaced points.
5. Base cleaningClean the base immediately before concreting.Base level after cleaning measured with a weighted tape.
6. Concreting, extractionPour continuously, logging concrete level against pipe depth; shorten the tremie as it rises; extract the casing after pouring.The tremie stays at least 3 m inside the concrete to prevent segregation.

Typical problems and remedies

ProblemCauseRemedy
Hole diameter too smallDrilling too fast, the tool not completing full turns at a levelRedrill where many sections are undersized; where few, add concrete spacers and rotate and raise the cage to scrape the wall
Hole collapsePoor fluid, heavy loads round the hole, drilling too fastControl the fluid closely; adjust drilling speed to the ground; keep vehicles and heavy loads away from the hole
Tremie blocked at the start of the pourPipe tip pushed into the soil at the basePull the whole tremie, clear it, reinstall and clean the base again before pouring
Tremie blocked during the pourSlump out of range, long wait for concretePull the tremie, redrill, remove the concrete placed and start again; if the concrete has hardened, abandon the pile and replace it as instructed by the designer

Acceptance

  • A record for each pile: coordinates, levels, depth, fluid and hole checks, cage inspection and the concrete pour log.
  • Pile integrity and load tests as specified by the designer.

Reference standards

The edition in force when the contract is signed applies.

  • TCVN 9395:2012 Bored piles – Construction and acceptance
  • TCVN 9393:2012 Piles – Standard test method in situ for piles under axial compressive load

Mots-clés

  • construction-method
  • bored-pile
  • foundation

Partager