벽·바닥 타일 시공 방법
이 글의 내용
  1. Preparation
  2. Wall tiling
  3. Floor tiling
  4. Acceptance criteria
  5. Common mistakes
  6. Reference standards

이 기사 본문은 영어판을 게재합니다. 한국어 번역은 준비 중입니다.

Wall and floor tiling in factory offices, toilets, canteens and corridors has to balance appearance with control of cutting waste. World Steel prepares detailed tiling layouts from the measured dimensions, tiles on accepted screeds and render, and checks flatness, falls and bond before handover.

벽·바닥 타일 시공 방법, 사진 12

Preparation

  • Tools: push tile cutter, angle grinder, paddle mixer, rubber mallet, notched trowel, mixing bucket, joint spacers (1 mm, 1.5 mm, 2 mm…), laser level, aluminium straightedge.
  • Tiles: the approved type; not warped or chipped; free of dust and oil. Absorbent tiles are soaked and drained before laying. Each floor area uses one batch so colour and size match.
  • Adhesive and mortar: approved tile adhesive, stored and used to the manufacturer's instructions; screed and render laid as for floor screeds and plastering.
  • Drawings: positions, finished levels, tile size and colour, setting-out tile, mortar grade, falls and directions. Check the measured dimensions and arrange the tiles to reduce waste.
  • Area: check floor levels and clear dimensions; screeds and render must be flat, plumb, square and well bonded, cleaned of dust and dampened before tiling.

Wall tiling

StepWork
1Set up the laser and establish the +1 m datum (taking the level from outside the room).
2Chalk the line of the bottom course one tile height above the floor; following the designed falls, the lowest wall tile matches the lowest point of the floor (at the drain).
3Use the laser to set square lines and chalk vertical reference lines on all four walls so wall and floor joints line up.
4Mark and drill the M&E openings in the wall.
5–6Cover the back of the tile fully with adhesive using a notched trowel; set the first bottom tile as the reference, tap evenly with a rubber mallet and level it both ways with a straightedge or spirit level.
7–8Set reference tiles from the first one; tile from the bottom up, checking with a straightedge every 3–4 tiles. Dry-lay to choose the pattern so adjacent tiles match in grain and colour.
9Always use joint spacers; remove them after 2–4 days and clean the joints.
10–12Mitre external corners at 45°; butt the tiles at internal corners; note where tiling stops and the width at door reveals for the frames.
13–14Grout the joints full, tight and neat; clean thoroughly and prepare for acceptance.

벽·바닥 타일 시공 방법, 사진 21

Floor tiling

  • Check the screed; hollow areas are broken out and relaid. Sweep clean and dampen the base.
  • From the setting-out tile on the approved drawing, chalk two lines at right angles and check them for square.
  • First lay one straight row along the longer reference line. Cover the back of the tile fully with adhesive or slurry using a notched trowel, especially at the corners so they are not hollow; tap with a rubber mallet from the centre outwards until the bed shows evenly round the tile.
  • Toilets: tile all the walls first, the far wall first; then the floor. The tile at the drain is cut to fit the drain neatly.
  • Fit skirting tiles after the floor, with joints matching the floor joints.
  • Clean the tile faces and joints, grout flush, straight, full and sharp; wipe grout off the tile faces immediately.
  • No traffic or impact until the tiles have set. Outdoor paving has movement joints every 4–6 m, 2 cm wide unless the design says otherwise, filled with a flexible material; shade and protect from rain for 1–3 days after laying.

벽·바닥 타일 시공 방법, 사진 22

Acceptance criteria

CriterionRequirement
Wall tile flatness (2 m straightedge)Gap ≤ 3 mm
Floor tile flatnessGap under the straightedge ≤ 3 mm
FallsDeviation ≤ 0.3%; water test or roll a 10 mm steel ball; relay where water ponds
Lippage between adjacent tiles≤ 0.5 mm
Joint between floor and bottom wall course (toilets)≤ 3 mm
BondNo hollow sound when tapped
SurfaceCorrect shape, size and pattern; no defects; even colour; free of mortar and cement

Common mistakes

MistakeRemedy
Screed or render not up to standardLay and accept as for screeds and plaster; scratch a diamond key into the render
Careless cutting and grinding, external corners not mitredMachine cut and mitre external corners at 45°
Chipped tiles, untidy or uneven jointsReplace tiles; sort tiles before laying; always use spacers
Uneven floorCheck flatness continuously; one batch per strip
Hollow tilesCheck the render and screed first; full, solid adhesive coverage
Tiles chipped by other tradesCorner tape, protective sheeting, mortar fillets at door edges; rubber wheels on scaffolds
Gaps between door trims and skirting tilesFinish the skirting tile at the trim after the trim is fixed

Reference standards

The edition in force when the contract is signed applies.

  • TCVN 9377-1:2012 Finishing works in construction – Part 1: Flooring and screeding works
  • TCVN 9377-3:2012 Finishing works in construction – Part 3: Wall tiling works
  • TCVN 5674:1992 Finishing works in construction – Execution and acceptance