Steel structures & roofing

Purlins, metal roofing and cladding, and deck slabs

Purlin forming, rolling and laying sheets, insulated roof build-up, deck slabs and roof safety, with the common mistakes that cause leaks.

  • World Steel Group
  • Published
  • 3 min read
Purlins, metal roofing and cladding, and deck slabs
In this article
  1. 1. Purlins
  2. 2. Roof and wall sheets
  3. 3. Insulated metal roof (typical build-up)
  4. 4. Deck slabs
  5. Safety when working on the roof
  6. Common mistakes
  7. Reference standards

Metal roofing and cladding decide how watertight, how well insulated and how durable a factory building is. World Steel controls every layer, from purlins and roof sheets to insulation and composite deck slabs for mezzanines and plant floors. This article sets out the fabrication and installation sequence and the main inspection points.

Purlins, metal roofing and cladding, and deck slabs, photo 12

1. Purlins

  • Purlin coil delivered to the workshop is checked for thickness before roll forming.
  • Roll formed on a purlin machine; each piece is labelled with its type, length and position.
  • On site, thickness and type are checked against the drawings again before installation; sag rods are fitted as designed.

2. Roof and wall sheets

StepWorkControl
1. Roll formingSheets longer than can be transported are roll formed on site.Profile, thickness and coating as specified.
2. LiftingUse purpose-made sheet clamps to lift sheets without denting the ribs.Never drag sheets across the roof.
3. LayingMove sheets into position and lay them in the designed direction; for standing seam roofs, close the seams with a seaming machine.Straight ribs, side laps, fixing to the purlins.
4. FlashingsFit eaves, gutters, ridge caps, gable flashings and details round vents and skylights.Seal every junction.

3. Insulated metal roof (typical build-up)

  1. Erect the Z purlins.
  2. Lay the mineral wool insulation.
  3. Fix cement board as the support layer.
  4. Bond the bituminous waterproofing membrane.
  5. Fix the clips for the standing seam sheets.
  6. Install the top roof sheets.

The exact build-up (thickness and density of the insulation, membrane type) follows the approved design.

4. Deck slabs

  • Lay deck sheets on the steel beams and fix them as designed; close the rib ends and slab edges so no grout is lost during the pour.
  • Fix slab reinforcement and spacers; check temporary propping (if the design requires it) before concreting.
  • Pour and cure as for a normal concrete slab.

Safety when working on the roof

  • Safety nets under the roofing area; lifelines along the roof.
  • No work in rain or strong wind; no loose sheets left on the roof at the end of a shift.

Common mistakes

MistakeConsequencePrevention
Purlins of the wrong thicknessRoof sag, insufficient capacityCheck thickness in the workshop and on delivery
Ribs dented when liftingLeaks at lapsUse sheet clamps; never drag sheets
Missing sealant at flashings, ridges and roof penetrationsLocal leaksAccept flashing details before scaffolding is removed
Deck rib ends not closedGrout loss, honeycombed slab soffitCheck before the pour

Reference standards

The edition in force when the contract is signed applies.

  • TCXDVN 170:2007 Steel structures – Fabrication, assembly and acceptance – Technical requirements
  • The approved installation instructions of the roof sheet manufacturer