Design and permits out of step
Changing the design after fire safety or environmental filings means rework and more waiting.
Stage 4/5 · FDI investment process
The longest stage, with the most parties involved. World Steel takes on design, permits, steel fabrication at the Hai Son factory and construction as one package, so design and permit filings move together.
Indicative duration: 150–180 days
Changing the design after fire safety or environmental filings means rework and more waiting.
Separate design, steel, civil and MEP contracts make responsibility and schedule hard to control.
Construction Law No. 135/2025/QH15 takes effect on 1 July 2026 and changes which works need a construction permit.
From concept to construction drawings: architecture, structure, MEP and BIM.
We check which steps apply: 1/500 plan, environment, fire safety, appraisal, construction permit or the special procedure.
Steel structures fabricated at the Hai Son factory to ISO 3834-2, EN 1090-2 EXC3 and AS/NZS 5131 CC3, then erected and built as one package.
Phase 4 150–180 days
The longest phase. World Steel can take on design, permits, steel fabrication and construction as one package.
Each design stage develops the previous one in more detail.
From 1 July 2026, Construction Law No. 135/2025/QH15 allows FEED or technical design in place of the basic design in the feasibility study.
The usual roadmap for a project in an industrial park. Days are indicative.
Under Law on Investment No. 143/2025/QH15 and Construction Law No. 135/2025/QH15, many industrial park projects can skip some of these steps, such as the building permit, by choosing the special procedure or when the works have been appraised by the construction authority. World Steel checks the roadmap that applies to each project.

Building density, green ratio, building height, setbacks and each park’s own regulations.
It depends. Under Construction Law No. 135/2025/QH15, works appraised by the construction authority need no construction permit; projects using the Article 28 special procedure of the Investment Law replace the permit with a commitment.
From 1 July 2026, Construction Law No. 135/2025/QH15 allows a FEED or technical design instead of the basic design in the feasibility study report.
EPC, design and build, general contracting, steel structure packages or a complete project design package.
Factory construction
Send us the building area, height, crane capacity (if any) and your target construction start.