Lease terms are hard to compare
Rent, management fees, payment schedules and handover conditions differ between industrial parks.
Stage 2/5 · FDI investment process
The plot sets your layout, foundations, utility connections and even your permit timeline. World Steel looks at it as the team that will design and build the factory on it.
Indicative duration: ~30 days
Rent, management fees, payment schedules and handover conditions differ between industrial parks.
Plot shape, orientation, ground level, density and setback rules can make the production layout inefficient.
MOU, deposit, investment registration, company set-up and land lease need to follow the right sequence.
We check zoning, utility connections and park building rules, and sketch your factory layout on the plot.
We place the same factory concept on each candidate plot to show the differences in cost and schedule.
We work alongside you with the park developer during negotiation and land handover.

Phase 2 ~30 days
Work with industrial park developers to secure the plot and the lease terms.
Deposit and payment shares are common practice in many industrial parks; each developer sets its own terms.
In many parks, about 10% is paid as a deposit at the MOU, about 50% at lease signing and the rest at land handover. Exact terms are set by each park developer.
Inside a park, infrastructure is in place and the special procedure of Article 28 of Investment Law No. 143/2025/QH15 may apply. Outside, land and infrastructure procedures usually take longer.
Once the site is secured by an MOU, the investor files for the Investment Registration Certificate, then sets up the company and signs the land lease.
Site selection